Overview
On 13 October Gas Industry Co received a request from Maui Development Limited (MDL) to consider and make a recommendation in respect of proposed changes to the Maui Pipeline Operating Code (MPOC).
The proposed change request and consultation timetable are shown below.
Application Appendix I: Industry Consultation document
Application Appendix II: Industry Feedback and MDL Comments document
Marked-up MPOC with proposed changes
Revised timetable
|
What |
Tentative date |
|
Call for initial submissions |
Mon 17 October 2011 |
|
Submissions due |
Mon 14 November 2011 |
| Call for cross-submissions | Fri 2 December 2011 |
| Cross-submissions due | Tues 31 January 2012 |
|
Draft Recommendation released for consultation |
Tues 14 February 2012 |
|
Submissions due |
Tues 13 March 2012 |
|
Final recommendation |
Tues 17 April 2012 |